ETHESDA,
Md., April 10 — Officials from an Ohio nuclear power plant assured
federal regulators today that they could repair corrosion that had
eaten nearly all the way through a reactor lid, but faced a barrage
of questions from the Nuclear Regulatory Commission staff.
Executives of the Davis-Besse nuclear plant near Toledo met with
commission officials to convince them that they could repair the
hole by filling it with a 13-inch stainless steel disk, welded into
place.
After a three-hour meeting, the executives left with a long list
of questions to answer, including how they would make sure that the
heat of a welder's torch would not further damage the metal.
Sixty-eight other reactors around the nation have a design
similar to Davis-Besse's, and the commission is trying to determine
if any of them have incurred the same kind of corrosion. All 68 have
said they did not, but some did not provide enough of a basis for
their assurances, said Ken Karwoski, a corrosion specialist with the
commission.
At Davis-Besse, which is owned by the FirstEnergy Corporation of Akron, Ohio, cooling water from the
reactor leaked from nozzles on the reactor head; boric acid, which
is mixed into the water to control the nuclear reaction, ate away
about 70 pounds of metal, going through six inches of exterior
steel.
When the 25-year-old reactor was shut for refueling and repair of
the nozzles this year, all that was left was a thin layer of steel
meant to control corrosion inside the vessel.
The regulators were shocked by the extent of the corrosion. Leaks
were well known, but government and industry officials believed that
when they occurred, the temperature at the vessel head, more than
600 degrees, would boil the water away and leave nothing but a
harmless boron powder.
After investigating, the commission staff concluded that the
Davis-Besse operators had missed many opportunities to find the
problem before it became so serious.
Critics of nuclear power agreed.
"When you're using a crowbar to knock the stuff off the reactor
head, it's a sign you've gone too far," said David Lochbaum, a
nuclear engineer with the Union of Concerned Scientists. Workers had
pried boric acid off the head during a refueling shutdown in
2000.
At the meeting today, about a dozen commission staff members
asked about the "repair concept" that company officials
presented.
"It's a first-of-a-kind repair," said Brian W. Sheron, associate
director for project licensing and technology assessment at the
commission. "The staff is very concerned that whatever we approve,
they are confident it is going to hold up."
One issue, Mr. Sheron said, was "just the sheer size of the weld"
— to hold in place a piece 13 inches in diameter and about 6 inches
thick.
FirstEnergy officials said the session had given them a clear
indication of what information their plan would need to include to
satisfy the commission. The company had hoped to submit that plan
next week but company executives said after the session that it
might take longer.
If contractors cannot repair the vessel head, the company plans
to replace it with the head from a reactor in Midland, Mich., that
was abandoned during construction, or the head of a retired plant in
Sacramento. They have also ordered a new reactor head, but do not
expect delivery before February 2004.
Delays are expensive because the plant employs 780 people,
whether or not it generates electricity; property taxes alone run
$500,000 a month. Officials hope to have the reactor running by
summer.
Opponents say that would be too soon. Christine Patronik-Holder,
a spokeswoman for the Safe Energy Communication Council, said that
until everyone agreed on exactly how the corrosion occurred, "plans
to place patches amount to little more than Russian roulette with
the lives of northern Ohioans."
But the company is proceeding to figure out repair details,
including how it will check for leaks when the work is
completed.
Radiation dosage in the repair area is so high that a welder
would absorb in two hours as much radiation as the industry usually
allows workers to incur in a year. In two and a half hours, the
welder would reach the annual limit the commission sets. So the plan
will rely on robot welders.
Indeed, radiation in the affected area is so high that it will be
a challenge just to X-ray the completed repairs to look for any
flaws. Framatome, the French reactor company that will do much of
the work, said it could compensate for the high background
radiation.