![]() |
| ||||||||||||
| » OR Search By Biz Name, Location | |||||
|
|
INSIDE News » The Plain Dealer » Newsflash » Weather » Traffic » Obituaries » Opinion » Business » Crime » Politics » Education
|
| |||||||||||||||||
News
Inspectors find new signs of rust at Davis-Besse
10/12/02
In a potentially serious new development, inspectors have found rust
stains where they had not found them before - on the bottom of the
Davis-Besse nuclear reactor. For the last seven months, officials at Davis-Besse and the Nuclear
Regulatory Commission have been focused on rust on the reactor's lid -
where leaking nozzles that passed through the lid ate a dangerous,
footprint-sized hole. Rust at the opposite end of the reactor could mean that nozzles there
may also have been leaking and causing corrosion in recent years. If laboratory tests now under way show the nozzles are cracked and that
reactor coolant has been seeping out, repairs could pose another major
obstacle to restarting the facility, which has been shut down since
February. FirstEnergy Corp., owner of the damaged power plant near Toledo, said
yesterday a contractor inspecting the bottom of the reactor discovered
what appeared to be boric acid deposits and rust stains on the reactor's
side and near some of the 52 nozzles, or tubes, that carry instrument
wiring through the base of the vessel. The instruments monitor the nuclear reaction in the reactor's core.
The light residues, called "trailings," may have formed when workers
spray-washed the reactor's lid during refueling shutdowns in the 1990s,
said company spokesman Todd Schneider. Or they might be tell-tale evidence of cracks in the instrument
nozzles, which are made of the same nickel alloy as those in the lid. "We don't believe there is any leaking from those nozzles," said
Schneider. Federal regulators, who learned of the situation this week, are taking
a wait-and-see approach. "There is no evidence at this point to show that they have leakage,"
said Jan Strasma, spokesman for the Nuclear Regulatory Commission. "I would not say the situation is serious at this point," he said.
"It's too soon to know." The agency has asked FirstEnergy to submit a
written report early next week, Strasma said. Boric acid, normally in the reactor's coolant to help enable nuclear
fission, leaked through cracks in the reactor's lid nozzles over several
years and ate a large rust hole through the 6½-inch steel lid - leaving
only a thin stainless steel liner to contain the reactor's radioactive
coolant. An inspector scraped samples of the residue from 12 of the bottom
nozzles in an attempt to determine whether the corrosion ran down from the
lid or leaked from a bottom nozzle. Some of the test results were
inconclusive, and further analysis has been ordered. The inconsistent lab results do "not necessarily show a leak,"
Schneider said. "It could be just the way the concentration of boric acid
built up, or the way the reactor head was cleaned at one time. "I wouldn't call it rust. It's more like staining, like washing a black
car with well water." Though the bottom nozzles are made of the same material as those that
cracked in the lid, the lower nozzles are not subjected to temperatures as
high as 600 degrees, Schneider said. "The temperature is much cooler, making these nozzles less susceptible
to cracking," he said. However, neither the industry nor the NRC fully understands how the
stress cracks form. Research is ongoing. FirstEnergy's contractor wrote a brief account of the initial
inspection of the reactor bottom after the stains were found on June 30. A
second summary was written on Sept. 30. While available to the agency, these so-called condition reports are
not formally submitted to the NRC, Strasma said. More than 7,000 such
reports have been compiled by workers and inspectors this year. The NRC has created a special committee to determine whether
FirstEnergy's repairs to the reactor and reforms of its management are
sufficient to allow the plant to restart. The company has pushed back its deadline to have the plant ready for
restarting until "early next year." But the NRC has final authority. To reach these Plain Dealer reporters: jfunk@plaind.com, 216-999-4138 jmangels@plaind.com, 216-999-4842
| |||||||||||||||||||
About Us | User Agreement | Privacy Policy | Help/Feedback | Advertise With Us © 2002 cleveland.com. All Rights Reserved. | |||||||||||||||||||