![]() |
| ||||||||||||
| » OR Search By Biz Name, Location | |||||
|
|
INSIDE News » The Plain Dealer » Newsflash » Weather » Traffic » Obituaries » Opinion » Business » Crime » Politics » Education
|
| |||||||||||||||||
News
Davis-Besse start-up is pushed back 10/08/02
The Davis-Besse nuclear power plant won't be ready to make electricity
until early next year, instead of the previous company forecast of Dec. 7.
And the total cost to replace its corroded reactor lid, fix other
equipment and buy replacement power may reach nearly $400 million - as
much as $115 million more than previously planned. FirstEnergy Corp., owner of the power plant, said the new costs
included $50 million in spending next year. The company had been trying to
contain the impact of Davis-Besse to this year. The company said the additional costs also include about $27 million
for maintenance that had been planned for the future. Another $136 million
covers the costs of purchasing electricity to replace Davis-Besse's output
this year. Stockholders, not rate payers, will eat all but $55 million to $75
million of the $400 million. That $55 million to $75 million - to replace
the lid - will be spread over future years. As a result of Davis-Besse
spending, FirstEnergy's profits this year could decline by up to 53 cents
per share. The Toledo-area plant has been down since February. Workers in March
discovered that leaking reactor coolant, undetected for at least six
years, had rusted a large hole in the reactor's 6½-inch-thick steel lid.
Most of the major repair work in the plant - including the installation
of the new lid - will be completed this year, corporate spokesman Ralph
DiNicola said. "But as some of the work moves to year's end, we know we
will be getting bills in '03," he said. "And some work will not be started
until the plant is running again," he said. The company also yesterday moved its restart target date from Dec. 7 to
"early next year." FirstEnergy cannot be more specific at this point,
DiNicola said, in part because it is working with hundreds of outside
contractors and in part because the Nuclear Regulatory Commission has the
final say. The NRC has made it clear that it intends to inspect all of the repairs
and newly installed equipment. Over the summer, for example, an agency
inspector found problems with the training of company-paid inspectors. The
NRC then ordered the company to retrain its inspectors and re-inspect the
entire containment building. This process is pushing up costs, according
to DiNicola. "This is an interactive process," DiNicola said. "We are listening to
the NRC. And we believe what we have provided today is a completely
accurate indication of where the schedule stands and the costs that we
expect to incur." Analyst reaction to the new cost figures was muted. "I don't think it's a huge event," said Paul Rizdon of McDonald
Investments. "We knew costs were going up. I was hoping they could contain
most of them in '02. But I think most analysts believed some costs would
roll into 2003 and the Dec. 7 restart date to be very aggressive." Most analysts are still convinced Davis-Besse is a one-time event, said
James Halloran, analyst with National City's Private Investor Group. "As long as they can get the thing started up in a reasonable time, say
March or April, they will be OK," Halloran said. "But if they go past the
one-year anniversary without any clear indication of when they will
restart, they will get into trouble." In the meantime, the stock will be volatile, said Rizdon. "It's going
to trade with every headline that comes across the wires," he said. FirstEnergy's stock price ended the day at $29.21, down 40 cents. To reach these Plain Dealer reporters: jfunk@plaind.com, 216-999-4138 jmangels@plaind.com, 216-999-4842
| |||||||||||||||||||
About Us | User Agreement | Privacy Policy | Help/Feedback | Advertise With Us © 2002 cleveland.com. All Rights Reserved. | |||||||||||||||||||