![]() |
| ||||||||||||
![]() |
![]() | ||||||||||||
| FIND A BUSINESS | » OR Search By Biz Name, Location | ||||
|
|
INSIDE Business » The Plain Dealer » Market Updates » Biz Flash » Technology » Personal Finance » Autos » Forums
|
| ||||||||||||||||||||||||||
Business News
NRC engineers wanted to shut Davis-Besse 07/06/02 Staff engineers at the Nuclear Regulatory Commission last fall wanted
their bosses to order the shutdown of the Davis-Besse nuclear power
station by year's end.
They feared there might be dangerous cracks in nozzles in the reactor's
lid. They were concerned about the lack of inspection information they
were getting from the plant, according to NRC documents. And they realized
FirstEnergy Corp. intended to operate the reactor without a new inspection
beyond the time the NRC considered prudent. But top NRC managers ultimately decided not to issue the order. They reasoned it was "very unlikely" that cracks would cause the lid to
rupture. They also judged that even if such an accident happened, the
public's risk was acceptably low. They went along with Davis-Besse's
request to operate six weeks beyond the Dec. 31 date the agency set for
inspecting other nuclear plants. What neither the NRC nor FirstEnergy, Davis-Besse's operator, knew was
that the reactor not only already had cracks, but also that acid in the
reactor's coolant had leaked through them and bored a 5- by 7-inch hole
all the way through the heavy steel lid. Only the lid's thin stainless steel liner, bulging into the hole, kept
the radioactive coolant from spewing into the reactor building in an
unprecedented accident. NRC Chairman Richard Meserve revealed the internal debate in a letter
this week responding to questions about the close call at Davis-Besse.
The questions came from U.S. Reps. Marcy Kaptur of Toledo and Edward
Markey of Boston. "Had we been aware of the degradation [rust hole], the agency would
have taken the appropriate regulatory actions to shut down the reactor for
the required inspection," Meserve wrote. The NRC's inspector general is examining how the decision to delay the
Davis-Besse inspection was reached, and whether it mirrored what the
inspector general found to be a flawed agency decision in a similar case
two years ago involving a reactor near New York City. "When Arthur Andersen gets it wrong, the shareholders pay the price,"
said Steve Fought, legislative director for Kaptur. "If the NRC gets it
wrong, everybody could end up paying the price." Fought said Kaptur's
congressional staff is reviewing Meserve's letter and its hundreds of
supporting documents. "It's not just a question about the company," he
said. "It's a question about how the NRC acted too." To justify a shutdown order, the NRC would have had to prove the action
was necessary to protect the public, Meserve wrote. Relying on FirstEnergy's own risk assessment calculations, the NRC
staff determined that operating the plant past Dec. 31 could increase the
risk of a reactor core-damaging accident beyond what the agency normally
would consider acceptable. But the chance of such an accident posing a
danger to the public was low enough to be within the agency's allowable
limits. Based on the information the agency had at the time, NRC managers
decided they didn't have enough reason to halt Davis-Besse's operation
early. "After considerable deliberation and increased [FirstEnergy] management
attention, it is the staff's judgment that sufficient information is
available to justify operation of the Davis-Besse facility until Feb. 16,"
according to a confidential NRC staff report issued Nov. 30, 2001. The
date was a compromise, since FirstEnergy originally had sought to operate
until March 31. During the shutdown, workers inspecting for cracks in the nozzles that
allow control rods to pass through the reactor lid accidentally found the
rust hole, covered by a thick layer of "lava-like" boric acid. The company
is estimating it will spend $200 million buying replacement power and
repairing the crippled reactor. The issue that prompted the debate within the NRC about what to do with
Davis-Besse began last year. In early 2001, operators of a nuclear plant
in South Carolina similar to Davis-Besse reported finding cracks in some
of the stainless-steel tubes, or nozzles, that allow the reactor's control
rods to pass through the lid and into the nuclear core. The cracks were large and threatened to encircle the nozzles,
increasing the risk they would fracture and shoot out of the lid,
propelled by the reactor's high operating pressure. The NRC last August alerted utilities across the nation operating all
69 pressurized water reactors like Davis-Besse. They asked 13 plants,
including Davis-Besse, that were at the greatest risk for having the kinds
of cracks found at the South Carolina facility to explain why they
believed their reactors could safely operate beyond Dec. 31. FirstEnergy said it had reviewed inspection records from 1998 and 2000
and had concluded that there was no sign of leakage from nozzle cracking.
It made this argument even though its own records showed that much of the
reactor lid was caked with brown/red deposits of boric acid more than an
inch thick and that workers had to use crowbars to remove the rock-hard
deposits. The company wanted to delay inspection until its long-scheduled April
1, 2002, shutdown for refueling. That way, costs would be lower and
inspectors' exposure to radiation would be limited. When the skeptical NRC staff asked for more information, FirstEnergy
promised that it would lower the temperature of the reactor to limit
growth of any cracks. It also pledged to defer inspection and maintenance
of safety systems to keep them available in case of an accident. Finally, the company told the NRC it would give reactor operators
special training on how to handle the kind of lid rupture the agency
believed could happen at Davis-Besse. In an August internal memo, an NRC analyst worried that the operators'
current level of training might be inadequate. "There is concern that the event would evolve in a different manner
than that expected by plant operators and cause confusion," a staffer in
the Division of Systems Safety and Analysis wrote. Union of Concerned Scientists nuclear engineer David Lochbaum said
using risk assessment analysis to justify a six-week extension is flawed,
charging that the NRC was merely looking for an excuse to allow the
company to continue operating. "If you think nozzles are broken and you are not allowed to operate
with broken nozzles, then I think your answer is that that is your
answer," Lochbaum said. "When you don't like that answer . . . you play with the numbers again.
That's what they did."
| ||||||||||||||||||||||||||||
About Us | User Agreement | Privacy Policy | Help/Feedback | Advertise With Us © 2002 cleveland.com. All Rights Reserved. | ||||||||||||||||||||||||||||