![]() |
| ||||||||||||
| » OR Search By Biz Name, Location | |||||
|
|
INSIDE News » The Plain Dealer » Newsflash » Weather » Traffic » Obituaries » Opinion » Business » Crime » Politics » Education
|
| |||||||||||||||||
News
Feds on Davis-Besse: Blame us, too 10/10/02
The Nuclear Regulatory Commission, FirstEnergy Corp. and the nuclear
industry all share blame for the mistakes and oversights that allowed a
rust hole to fester unnoticed for years in the lid of the Davis-Besse
nuclear reactor. "We and the industry recognized the potential for this type of event 10
years ago," but along with FirstEnergy, failed to piece together the clues
that were piling up at Davis-Besse, said Ed Hackett, the co-author of a
scathing 96-page NRC report released yesterday. The "lessons learned" study, which the agency sometimes undertakes to
critique its performance in the wake of major problems at nuclear plants,
recommends significant changes in the NRC's supervision of reactor
operators. It calls for more scrutiny and skepticism, as well as stronger
follow-up to make sure utilities are doing what they promise. But FirstEnergy bears much of the responsibility for the unprecedented
rust hole, which took the Toledo-area plant to the brink of a serious
accident, the NRC report concludes. The company ignored problems,
misinterpreted information, slashed its engineering budget and kept vital
information from the NRC that might have helped catch the lid damage much
sooner. U.S. Sen. George Voinovich, Republican of Ohio, who was briefed by NRC
Chairman Richard Meserve, called the findings "serious and troubling."
He called for congressional hearings and a General Accounting Office
investigation into the Davis-Besse affair, joining U.S. Rep. Dennis
Kucinich, the Cleveland Democrat, who previously called for such hearings.
Both Voinovich, a strong supporter of nuclear power, and Kucinich, a
longtime critic of FirstEnergy, serve on committees that oversee the NRC.
The NRC report's 52 recommendations will be reviewed by a team of
senior agency officials. They will decide which ones merit action. The increased oversight the
study calls for no doubt will require more dollars and staff, its authors
said. The agency's budget comes mostly from fees paid by the nuclear
industry, and it will be up to a cost-conscious and heavily lobbied
Congress to determine if it should grow. "The tough job is the follow-up," said report co-author Joe Donoghue.
"Our charter was to look hard and tell [NRC management] what needs to get
done. The next group has to decide where to get the money and resources."
Although lacking in some areas, the report does "a good job of
identifying some problems that need to be fixed," said David Lochbaum, a
nuclear safety engineer with the Union of Concerned Scientists, a watchdog
group. "You can only juggle so many balls," he said of the NRC, whose staff
and money cuts in its Midwest office challenged the agency's ability to
oversee Davis-Besse, according to the report. "They need the resources to
make things happen." Otherwise, the study "is just going to go up on a
shelf." They also need relief from congressional pressure to fast-track
nuclear industry demands, Lochbaum said. Other watchdog groups - Ohio Citizen Action and the Nuclear Information
and Resource Service - faulted the report for not probing the NRC's
decision last fall to let Davis-Besse delay a shutdown to inspect its
reactor lid. The NRC report was sharply critical of the agency's own multiple
failures to identify glaringly obvious problems at Davis-Besse throughout
the 1990s. More broadly, the agency mishandled the industrywide problem of
stress cracks in the reactor lid that allowed coolant to leak and corrode
metal parts. The report says that the NRC was wrong to go along with the American
nuclear industry's assessment that such lid cracks weren't a safety risk
and that corrosion could be easily spotted long before it caused a
problem. Rather than focus on preventing such leaks, as the French nuclear
industry did by replacing reactor lids, the NRC chose to encourage reactor
operators to find ways to catch the oozing cracks early. However, the
report said, the NRC did not press nuclear plants to install equipment
that would detect tiny amounts of spilled coolant. The task force found that NRC has done a poor job sharing information
about plant conditions and research results. For example, a former NRC
senior inspector based at Davis-Besse said he knew in 2000 that plant
workers had found clumps of acid left behind when spilled coolant
evaporated from the hot reactor lid. "However, he decided not to perform inspection follow-up and did not
notify his supervisor," the report said. The NRC inspector didn't think
that the built-up acid was significant, and thought that the company -
which the agency viewed as a "good performer" - would clean it up. The report also cited problems with the process the NRC uses to alert
reactor operators to potentially dangerous conditions that might affect
similar plants. From 1980 to 2002, the NRC issued 17 bulletins,
information notices and other warnings to utilities about leakage and
corrosion incidents, and yet the problems continued at many nuclear
plants. "This calls into question the effectiveness of the process as a
catalyst for addressing issues," the task force said. For example, in 1997, the NRC asked all plants to provide their plans
for inspecting reactor lids for cracks. Davis-Besse had not planned to do
the detailed crack inspections the NRC wanted until 2002. FirstEnergy was more intent on keeping the reactor running to make
electricity than on safety issues, the report said. The company accepted
degraded equipment rather than fixing or replacing it, failed to learn
from previous brushes with corrosion damage, and cut its engineering
budget by 60 percent and staff by 44 percent from 1991 to 2001. The heavy
workload and high turnover hurt the plant staff's ability to diagnose the
signs of corrosion. "The report provides some valuable insights," said FirstEnergy
spokesman Todd Schneider. "We've said we made mistakes, missed
opportunities. Most importantly, we're putting into place more procedures
and processes to make sure this doesn't happen again." To reach these Plain Dealer reporters: jmangels@plaind.com, 216-999-4842 jfunk@plaind.com, 216-999-4138
| |||||||||||||||||||
About Us | User Agreement | Privacy Policy | Help/Feedback | Advertise With Us © 2002 cleveland.com. All Rights Reserved. | |||||||||||||||||||