| November 30,
2004
Mr. John A. Grobe, Chairman
Davis-Besse 0350 Panel
United States Nuclear Regulatory Commission
2443 Warrenville Road, Suite 210
Lisle, IL 60532-4352
SUBJECT: DAVIS-BESSE MID-CYCLE OUTAGE SCOPE
Dear Mr. Grobe:
The recent finding by the Nuclear Regulatory
Commission that FirstEnergy failed to properly report the emergency siren
performance indicator for Davis-Besse is among the ample evidence for
continued regulatory oversight of this facility by your 0350 Panel.
FirstEnergy plans a mid-cycle outage at Davis-Besse in the
near future. The NRC should take this opportunity to investigate whether
adequate safety margins exist for the two reactor coolant pumps (RCPs)
that FirstEnergy opted not to repair during the 2002-2004 outage. A year
ago, FirstEnergy informed the NRC that it had replaced the casing-to-cover
gaskets on RCPs 1-1 and 1-2. FirstEnergy additionally reported that "Results
of that testing [September 2003] indicate that the case-to-cover gaskets
[for RCPs 2-1 and 2-2] have performed as designed and indicate that they
are nearing the end of their operational life." It would be very
prudent and entirely consistent with an oft-asserted "safety first"
approach for FirstEnergy to conduct testing and/or inspections of RCPs
2-1 and 2-2 to determine if the case-to-cover gaskets still have operational
life remaining.
The mid-cycle outage would also provide an excellent opportunity
for the NRC to assess the results from the Bentley-Nevada diagnostic equipment
installed on all four RCPs during the 2002-2004 outage. Focused NRC attention
to this area seems warranted given this NRC finding:
The team determined that the licensee's evaluations [of
RCP case-to-cover gasket leakage] were based on testing that: (1) did
not use the same methodology from outage to outage; (2) did not attempt
to normalize the data from outage to outage; (3) did not consider the
impact of reactor coolant pressure and temperature conditions on the test
results; and (4) was only intended to verify that the leak detection lines
were open and not blocked.
The newly installed Bentley-Nevada diagnostic equipment
provides data on pump performance. The NRC should evaluate how FirstEnergy
has integrated this data with past data to verify, among other things,
that FirstEnergy is not using the data simply to ensure the pump is running.
We would respectfully request that the NRC outline its planned
inspection activities related to the reactor coolant pumps during the
mid-cycle operation at the next 0350 panel meeting, which we believe is
scheduled for December 6, 2004. We expect that the results from these
NRC inspection efforts will be recorded in future inspection report(s).
Sincerely,
|