By
Malia Rulon
The Associated
Press
WASHINGTON
- Davis-Besse nuclear plant's plan to fix a flaw in
emergency cooling pumps by installing a metal debris strainer
is not guaranteed approval, federal regulators said Tuesday.
The Nuclear Regulatory Commission must sign off on the
repairs before the plant near Toledo can restart.
Plant engineers discovered in March that small particles
could pass through the pumps' filters and damage the pumps'
bearings, causing them to fail. The emergency pumps keep the
hot, radioactive reactor core supplied with coolant in case of
a rupture. There is no backup.
Bob Coward, an engineer with plant owner FirstEnergy Corp.,
told NRC officials Tuesday that the strainer was tested over
several days using particles of different sizes and density.
"We actually skewed our debris particles smaller to allow
them to get through the pump strainer," he said, adding that
the pump was able to withstand the tests.
If the plant goes ahead with the fix, it is doing so at the
risk that NRC officials won't approve the finished pumps,
regulators said.
"You've answered a number of questions from the NRC staff,
but you should not infer that we have found this pump to be
acceptable at this stage," said Bill Ruland, NRC project
director for nuclear power plants in the Midwest.
The plant along Lake Erie near Toledo has been shut down
since February 2002. A month later a leak was discovered that
had allowed boric acid to eat nearly through the 6-inch-thick
steel cap covering the plant's reactor vessel. Akron-based
FirstEnergy hopes to restart the plant this fall.
The modification plan likely will pass muster, said David
Lochbaum, a nuclear safety engineer and industry watchdog for
the Union of Concerned Scientists.
"I feel good that the tests are already completed," he
said. "Anything can look good on paper, but they have already
run this design for 21 days."
The pump modification is expected to cost $7 million,
FirstEnergy spokesman Todd Schneider said. Replacing the pumps
would cost much more because Davis-Besse is the only plant in
the nation whose emergency high-pressure pumps are designed
this way.
Meanwhile, a report released Tuesday by the NRC's inspector
general said government inspectors at the plant failed to pass
along reports of numerous instances of boric-acid leaks and
corrosion to agency headquarters.
That caused the agency to miss warning signs of the
corrosion, which the agency said was the most extensive ever
found on top of a U.S. nuclear plant reactor.
The inspector general prepared the report after Ohio Rep.
Dennis Kucinich asked for a closer look at NRC oversight of
the Davis-Besse plant. Kucinich, running for the Democratic
presidential nomination, said the report "demonstrates a
complete failure at every rung of NRC's bureaucratic ladder."
NRC spokeswoman Sue Gagner said the agency was studying the
findings.
TOP
STORIES
Main
Street plan unites beer, Bootsy
Report
slams sewer brass
Teens
learn dangers of Butler roads
'Scrunci
bandit' suspect arrested
IN
THE TRISTATE
Law
lets parents weigh in on rehirings
Building
would alter Hyde Park Square
County
weighs 2 levies
Rape
claim investigated at Woodward
Workshop
shows how to preserve open space
Regional
Report
ENQUIRER
COLUMNISTS
Bronson:
Protect the unions, soak the city taxpayers
again
Howard:
Good Things Happening
BUTLER,
WARREN, CLERMONT
Driver
of Mustang accused of kidnap try
School
locked after bank robbed
Wall
visit evokes 'Nam tales
Investors
to try developing Wooster
No
plan 'preferred,' officials say
Waynesville
landlord, 73, faces drug peddling charge
Warren
United Way director leaves drive before
conclusion
Lebanon
school levy backed
OBITUARIES
Guy
Westmoreland, 60, was author and librarian
Kentucky
obituaries
OHIO
Feds
wary of Davis-Besse's pump-fix plan
School
funding appeal unheard
Ohio
Moments
KENTUCKY
Man
free on bond in boat wreck
Kentucky
News Briefs
Jury
in Lambert case needs more time
4
days in another's shoes
Independence
mulls new taxes in face of $600K shortfall