![]() |
| ||||||||||||
|
|
INSIDE News » The Plain Dealer » Newsflash » Weather » Traffic » Obituaries » Opinion » Business » Crime » Politics » Education
|
| ||||||||||||||||||||
News
Davis-Besse pump plan under fire 03/28/03
FirstEnergy Corp.'s plan to delay rebuilding two huge reactor coolant
pumps at the Davis-Besse nuclear plant is drawing heavy criticism from
watchdog groups and a congressman. The pumps have a history of leaking.
The delay not only poses an equipment risk, the groups say, but also
shows that Davis-Besse's management - without challenge from federal
regulators - is still putting production over safety. That attitude is what got the Toledo-area plant in trouble to begin
with, when company managers for years ignored leaks in the reactor's lid
that eventually rusted through the barrier, said Paul Gunter of the
Nuclear Information and Resource Service. "Sound familiar?" agreed David Lochbaum, nuclear safety engineer with
the Union of Concerned Scientists, who yesterday issued a report critical
of both FirstEnergy and the Nuclear Regulatory Commission, which is
overseeing the plant's renovation. It has been shut down for 13 months.
Also yesterday, U.S. Rep. Dennis Kucinich cited the pump issue as yet
another reason why Davis-Besse's operating license ought to be revoked.
The Cleveland Democrat had petitioned the NRC last month to yank the
plant's license and has now amended that request to include the pump
concern. A FirstEnergy spokesman said the pumps will be checked for leaks, and
if necessary, repaired before Davis-Besse is put back in service. The
company is racing to have the plant ready by summer, but the NRC has said
many issues remain unresolved. The massive pumps are part of a group of four, two of which have been
rebuilt during the plant's current outage. Each is designed to move 90,000
gallons per minute, keeping coolant water circulating in and out of the
reactor vessel. The pumps shoot coolant through a loop of pipes, moving it
from the reactor core, where the liquid is superheated, to nearby tanks.
There the coolant's energy is used to create steam to make electricity.
Then the pumps push the coolant back into the core to repeat the cycle.
Each pump has a set of two gaskets that have been prone to leakage in
the past. The company's pump contractor last July recommended "a
comprehensive pump inspection/ refurbishment plan" in which the gaskets in
all four pumps would be replaced with an improved model and their spinning
parts would be checked for cracks. In August, two Davis-Besse supervisors made similar recommendations.
But after further study by a team of company and outside engineers, the
plant's top managers decided it was acceptable to rebuild only two of the
pumps. They reasoned that since all four had been rebuilt in 1986 and had an
expected operating life of 20 years before needing another overhaul,
electing to work on two now and the others in a year or two was actually
getting ahead of schedule. Left unspoken by the company, though, was that tests during a plant
outage in 1998 showed the two unserviced pumps were leaking, and one of
them was leaking during the next round of tests in 2000. Davis-Besse
workers did not leak-test the two pumps in question in 2002, nor did they
check the pumps' rotating parts for cracks, even though they found such a
crack in one of the pumps they elected to rebuild. "That's like saying a car is supposed to have maintenance at 30,000
miles, and I've got an indication of something serious happening at 20,000
miles but I'm not going to deal with it," said Paul Blanch, an electrical
engineer and veteran nuclear plant employee and consultant. "I don't buy
that." Former Davis-Besse engineer Andrew Siemaszko claims FirstEnergy fired
him last September because he raised safety concerns about the decision to
put off rebuilding the two pumps. He alleges the company has chosen not to
refurbish the pumps now because they are significantly harder to get to
than the two it has repaired, requiring more time and expense. Siemaszko has filed a whistleblower complaint with the U.S. Department
of Labor in an effort to get his job back. Siemaszko "is very gratified" by the support of Kucinich and the
watchdog groups regarding the pump issue, his attorney, Billie Garde, said
yesterday. He is worried both about the possibility of pump problems and
the implication that Davis-Besse's management is not fully reformed, Garde
said. The NRC is investigating whether there is merit to Siemaszko's pump
concerns. The issue "is already under evaluation by the NRC, and we are
discussing it with the utility," said Jack Grobe, who chairs the panel
overseeing FirstEnergy's efforts to return Davis-Besse to service. That
panel must be satisfied the plant can operate safely before giving
FirstEnergy permission to restart, Grobe said. Davis-Besse is preparing for a crucial test next month of the entire
reactor coolant system's leak-tightness. If the two coolant pumps that
have not yet been rebuilt show signs of leakage during that test, they'll
be fixed prior to the plant's restart rather than a year or two from now,
said spokesman Richard Wilkins. "The pumps will be tested and inspected for leaks when we do that
[reactor] test," Wilkins said. "At this point we don't believe we have any
[pump] leakage, and that will be validated through the test." To reach these Plain Dealer reporters: jmangels@plaind.com, 216-999-4842 jfunk@plaind.com, 216-999-4138
| ||||||||||||||||||||||
About Us | Help/Feedback | Advertise With Us Use of this site constitutes acceptance of our User Agreement. Please read our Privacy Policy. ©2003 cleveland.com. All Rights Reserved.
| ||||||||||||||||||||||