![]() |
| ||||||||||||
![]() |
|||||||||||||
|
|
INSIDE Business » The Plain Dealer » Market Updates » Biz Flash » Technology » Personal Finance » Autos » Forums
|
![]()
| ||||||||||||||||||||||||||
Business News
Davis-Besse costs still rising 03/12/03
Oak Harbor - FirstEnergy Corp. said yesterday the severe weather has
pushed up power replacement costs for its damaged Davis-Besse nuclear
plant to $40 million for January and February, compared to the $20 million
to $30 million forecast. The increase raises to $338 million the amount the company has spent on
repairs and replacement power - plus $50 million budgeted for repairs this
year - since the plant was shut Feb. 16, 2002, for refueling and an
NRC-mandated inspection. During a safety check of its lid last March, workers found a gaping
rust hole. Last night, workers repairing the Toledo-area plant reached a milestone
when they began bolting down a new 150-ton lid onto the reactor. The job, which began as federal authorities held their monthly meeting
with Davis-Besse managers at nearby Camp Perry, will take several days to
complete. Each of the 60 bolts must be tightened to exact specifications.
Still to come are two crucial tests - checking the reactor for leaks in
instrument tubes that pass through its bottom and checking the reactor's
containment building for air-tightness. Workers also must finish modifications to the emergency sump pump
debris screens. On top of that, thousands of smaller jobs remain to be done before the
plant can be restarted. "Restart is not imminent," said Jack Grobe, chairman of the special
Nuclear Regulatory Committee overseeing repairs and management changes
being made by plant owner FirstEnergy Corp. of Akron. "They continue to make good progress," he said. "They have three
challenges - design issues, safety culture and bulk work." Grobe could not predict when the NRC's army of inspectors would finish
their jobs. The company maintains the plant will be ready to restart
sometime in April. Among "bulk work" Grobe referred to are some 2,400 jobs, most minor,
that must be done, documented and inspected. The NRC will have 19
inspectors at the plant next week, he said. "There is a lot of hard work ahead of us," said Lew Myers, chief
operating officer of FirstEnergy's nuclear operating company. "But we are
making a lot of progress improving material [hardware] conditions." The NRC has demanded the company demonstrate that Davis-Besse's "safety
culture" - its overriding commitment to safety - is paramount before it
will allow the plant to make electricity again. Two months ago, the company hired industrial psychologist Sonja Haber
of New York City to review its "safety culture" and develop a program the
company can use to monitor and maintain it. Haber and her associates interviewed 90 FirstEnergy employees,
including senior managers, corporate executives, Davis-Besse managers and
workers throughout the plant, said William Pearce, vice president of
oversight for FirstEnergy's nuclear operating company. Another team attended routine plant meetings to see how day-to-day
decisions were made, he said. Finally, Haber gave a written survey to 661
of Davis-Besse's 830 employees. Haber will deliver her initial report to the company and NRC officials
next week. Concerned that the final report will be cleansed of
controversy, Grobe said the draft report ought to be attached to the final
analysis. "It's important that Haber's work be completely independent," Grobe
said. "Credibility is critical." Pearce said he did not know if the draft report will be made public.
Grobe said Haber's report will not be the last word on the issue. The
report will not be a "go, no-go, not a light switch," he said. The NRC will make its own assessment of Davis-Besse's safety culture
after sending a team of up to four inspectors, including two outside
experts, to the plant, he said. Design issues on Grobe's agenda stem in part from Davis-Besse's
engineers giving the go-ahead on equipment modifications before they have
completed final blueprints. The practice is called "at-risk design"
because there is a risk the job will have to be reworked when things don't
go together correctly. It has resulted in some problems. For example, plumbers, electricians and other craftsmen ran into
trouble installing newly rebuilt air conditioners in the reactor's
containment building. The three coolers, each containing 12 radiators, are
crucial to keeping the building temperature down after an accident.
Workers pointed out engineering designs would make it difficult to inspect
the coolers. Modifications are being made. "In a typical outage, you order parts and prepare for it months
before," said Myers. But because Davis-Besse is getting so many
improvements as problems are discovered, the company has had to engineer
on the fly. "It's . . . not the best way to do modifications," he said.
Grobe said the procedure does not violate NRC rules. To reach this Plain Dealer reporter: jfunk@plaind.com, 216-999-4138
| ||||||||||||||||||||||||||||
About Us | Help/Feedback | Advertise With Us Use of this site constitutes acceptance of our User Agreement. Please read our Privacy Policy. ©2003 cleveland.com. All Rights Reserved.
| ||||||||||||||||||||||||||||