![]() |
| ||||||||||||
|
|
INSIDE Business » The Plain Dealer » Market Updates » Biz Flash » Technology » Personal Finance » Autos » Forums
|
| ||||||||||||||||||||||||||
Business News
Davis-Besse failure linked to new rules 05/16/03
Washington- When nuclear regulators fixed blame for failing to notice
that there was a hole in the lid of the Davis-Besse reactor in Ohio, they
spent little time criticizing the role played by their new oversight
rules. Those rules, seeking to reduce overly burdensome regulations, in 2000
replaced the subjective, nit-picky set of guidelines that had governed
power plant inspections for years. But documents obtained by a watchdog group show that a special Nuclear
Regulatory Commission task force last year had in fact intended to blame
the new regulatory system in part for the slipshod inspections at
Davis-Besse. Before the task force's report was complete, however, NRC
staff had removed a section on the shortcomings of the NRC's new reactor
oversight process. The final report - an indictment on the agency and plant owner
FirstEnergy Corp. - did list possible improvement to the oversight
process. But it was far less sweeping and less critical than the earlier
suggestions. The NRC thus avoided the public criticism that most likely would have
resulted if it had more clearly linked the Davis-Besse failure to
weaknesses in its new regulatory regimen. And, says Jim Riccio, nuclear
policy analyst for Greenpeace, the omissions resulted in NRC commissioners
getting an incomplete and sanitized assessment of the agency's failure at
Davis-Besse. "Since the implementation of the new oversight process, NRC senior
management has continued to scuttle efforts of its own staff to regulate
the industry and has allowed reactors to operate to the point of
breakdown," Riccio told a meeting of NRC commissioners yesterday. U.S. Rep. Dennis Kucinich, a Cleveland Democrat who has criticized the
NRC's handling of Davis-Besse, said later in a telephone interview that
the omissions are "further evidence that the NRC continues to brush aside
safety concerns. "They're more interested in power plant profits," Kucinich said. NRC commissioners reject those criticisms. They said they do not know
why changes were made to the task force report, but they assumed there
were good reasons such as staff disagreements. They also thought the new
regulatory system was an improvement that will continually evolve. "I believe I am so far apart from where you are that it's not even
funny," NRC Chairman Nils Diaz told Riccio. Workers at Davis-Besse, near Toledo, discovered a pineapple-size hole
in the lid of the reactor in March 2002, leaving only a thin, cracked
liner to protect the reactor. The NRC assigned a task force to examine how
the NRC and industry failed to notice that boric acid corrosion had been
accumulating on the lid for years. The Lessons Learned Task Force issued
its report on Sept. 30. Riccio, using the Freedom of Information Act, recently obtained
unreleased drafts of the report from last August and noticed that material
had been left out of the final version. Yesterday, he asked the NRC's
inspector general to investigate the omissions. William Travers, NRC
executive director for operations, said that while the agency itself will
also look at the matter, the inspector general typically would take the
lead in determining whether something improper had occurred. Arthur Howell, the Texas-based NRC official who headed the Davis-Besse
Lessons Learned Task Force, said through a spokesman that material was
excluded from the report because it fell outside the scope of the task
force's mission. The spokesman said Howell was not available to discuss
the specific scope of the task force's work. In its final report, the task force stated an objective that was
exceptionally broad: to independently evaluate the NRC's regulatory
processes "in order to identify and recommend areas for improvement that
may be applicable to either the NRC or the nuclear industry." The NRC changed the way it regulates in recent years, fully adapting in
2000 a new approach to guide its plant inspections, shut-down orders and
report cards on nuclear plant safety. This occurred after nuclear plant owners complained to Congress in the
1990s that the NRC was arbitrarily citing them for picayune violations
with little bearing on safety. Congress threatened to decimate the NRC's
budget unless it backed off. Even NRC critics agreed the old system left too much leeway for NRC
staff interpretation. But some say the new system goes overboard in the
other direction, and drafts of the Lessons Learned report show some NRC
staff agree. The new oversight process mandates inspection of reactor systems and
components that are most prone to failure, as determined by agency
experience and engineering and mathematical modeling. Some NRC inspectors
consider the oversight regimen to be too rigid, with checklists guiding
inspections of only certain systems - and excluding, until now, passive
systems such as reactor lids. Unless a suspicious condition is deemed clearly dangerous, the new
process doesn't allow the implementation of other than routine
inspections, a draft of the lessons-learned report said. "The new oversight process does not regulate the industry, it regulates
the agency," Riccio told the commissioners, adding that it "handcuffs" NRC
regional inspectors. To reach this Plain Dealer reporter: skoff@plaind.com, 216-999-4212
| ||||||||||||||||||||||||||||
About Us | Help/Feedback | Advertise With Us Use of this site constitutes acceptance of our User Agreement. Please read our Privacy Policy. ©2003 cleveland.com. All Rights Reserved.
| ||||||||||||||||||||||||||||