![]() |
| ||||||||||||
|
|
INSIDE News » The Plain Dealer » Newsflash » Weather » Traffic » Paid Death Notices » News Obituaries » PD Obituaries » Opinion » Business » Crime » Politics » Education
|
| ||||||||||||||||||||
News
NRC reacts to Davis-Besse flaws 06/11/03
Design flaws uncovered in a part of the emergency core cooling system
at the Davis-Besse nuclear power plant have prompted the Nuclear
Regulatory Commission to ask the operators of similar reactors nationwide
to prove their emergency cooling systems will operate in a crisis. The NRC yesterday issued a bulletin to owners of 68 other high-pressure
reactors. The agency wants to know within 60 days why the utilities think
the emergency sumps in the reactor containment buildings are capable of
handling the thousands of gallons of coolant that would explode out of a
reactor during a major accident. The NRC has been aware for nearly two decades that debris blown about
the containment building by a high-pressure geyser of coolant from a pipe
break or other rupture could clog the sumps - and starve emergency pumps
pushing the coolant back into the reactor core. The agency and industry
groups have researched the problem and possible fixes for years without
coming to a definitive conclusion, partly, say critics, because of the
high cost of redesigning the sumps and partly because no plants are
identical. Agency researchers last August concluded that debris screens on sumps
of the general design found in most reactor buildings could either clog or
collapse under the weight of debris following an accident. And a Los
Alamos National Laboratories risk study for the NRC released in February
suggested strategies to reduce the risk of a catastrophe caused by sump
failure. But it was the work of Davis-Besse's engineers that added urgency to
the need to take action, said David Matthews, the NRC's director of
regulatory improvement programs. Davis-Besse's engineering study detailed the weaknesses of the
Toledo-area's plant's sump in a thorough analysis last December that
predicted the sump's debris screen would clog and the emergency pumps
would fail in a major accident. And this spring, the company declared that a pair of emergency pumps
designed to force water back into the reactor before its
one-ton-per-square-inch pressures are blown off could, under certain
conditions, clog even if the sump's debris screen did not. Because there is no backup system to the sump and its emergency pumps,
a failure of any part of the system could lead to a meltdown of the
reactor's nuclear core - challenging the reactor building's ability to
keep the radioactivity out of the environment. "When you get a plant declaring it themselves, you have sufficient
information [for a bulletin], said Matthews. Before that, all arguments
were theoretical, he said. Davis-Besse not only declared its sumps a major safety problem. Plant
owner FirstEnergy Corp. had its engineers and contractors completely
redesign and rebuild Davis-Besse's sump for $3.8 million, expanding the
surface area of its debris filters from 50 square feet to about 1200
square feet, said spokesman Todd Schneider. "Our new design is
cutting-edge." Yesterday's bulletin asks each plant owner whether an engineering
analysis has been done, how thorough it was, and whether top officials can
swear under oath that the sumps and related equipment will work after a
major accident. Plant owners who have not done a rigorous study, or whose examinations
turned up design problems, must tell inspectors what their staffs are
doing to compensate for the shortcomings while a permanent fix is
developed. The speed with which the NRC is moving has apparently surprised the
industry, which is still developing a model sump analysis for plant owners
to use in diagnosing their sump problems, said John Butler of the Nuclear
Energy Institute, the industry's lobbying arm. He said until recently the plan was that the NRC was not going to issue
a bulletin but instead a less hard-nosed "generic letter" - bureacratese
for a typical way of alerting plant owners of a problem and requesting
possible solutions, a process that can take from months to years. NRC engineers are now working on that letter, and the agency will issue
it in a few weeks, said Matthews. It will ask for suggestions about how to
permanently solve the sump problem. In the meantime, the bulletin will
provide the agency with the plant-specific information it needs, he said.
The letter-and-comment strategy could take months, said Paul Gunther of
the Nuclear Information and Resource Service, a critic of the NRC. "We remain concerned that the pace moves like molasses," Gunther said.
"They have talked about this for at least a decade. It's time for action,
not more talk." For complete coverage of Davis-Besse, go to
www.cleveland.com/davisbesse/ To reach this Plain Dealer reporter: jfunk@plaind.com, 216-999-4138
| ||||||||||||||||||||||
About Us | Help/Feedback | Advertise With Us Use of this site constitutes acceptance of our User Agreement. Please read our Privacy Policy. ©2003 cleveland.com. All Rights Reserved.
| ||||||||||||||||||||||