![]() |
| ||||||||||||
![]() |
![]() | ||||||||||||
|
|
INSIDE Business » The Plain Dealer » Market Updates » Biz Flash » Technology » Personal Finance » Autos » Forums
|
![]()
| ||||||||||||||||||||||||||
Business News
NRC tests may delay reopening of plant 02/25/03
Washington- Nuclear regulators say the damaged Davis-Besse nuclear
power plant near Toledo might not reopen until May or later. That would pose a new setback to FirstEnergy Corp., which is spending
$10 million to $12 million a month on replacement electricity for its
customers. Davis-Besse has been closed since last February, when it shut
down for a government-requested inspection that turned up an unprecedented
corrosion hole in the reactor's thick steel lid. The hole was created by
leaking, unchecked boric acid. "There is a lot of inspection activity taking place. We have
inspections that are laid out through this April and May, matter of fact,"
said Bill Dean, co-chairman of a Nuclear Regulatory Commission panel that
must give approval before the plant can restart. Approval, Dean said,
won't come until all the inspections are complete. One inspection, for leaks at the bottom of the reactor, won't be done
until mid- to late March, Dean said. And inspections to make sure the
plant's "safety culture" has improved - an awareness by Davis-Besse
management and staff that the past sloth is unacceptable and harmful -
will continue through May, Dean said. "So that's our current schedule. They continue to change their schedule
as things occur," he said of FirstEnergy. "This is typical behavior for a
plant during an extended shutdown. As time goes on, either they find
additional things or it takes them longer to fix something" already
identified as needing repair. First Energy spokesman Todd Schneider acknowledged in a telephone
interview that "the NRC ultimately decides when we're going to restart."
"But we think we're going to have everything ready for restart in
April," Schneider said. But Brian Sheron, NRC associate director of project licensing, said,
"The bottom line is, we're not working for the licensee's schedule. The
licensee may be ready to start up long before the agency is willing to say
they've corrected all the deficiencies which led to this and we have
reasonable assurance that they can start up and operate the plant safely.
Those are two different dates." The NRC officials made their comments yesterday while talking to
reporters in Rockville, Md., after a public hearing on a new inspection
program announced on Feb. 11. The program requires not only visual
inspections for cracks or damage to reactor lids but also tests using
ultrasound, eddy current or dye penetrant to check the nozzles that pass
through the lids. The program covers Davis-Besse and the 68 other
pressurized-water reactors throughout the United States. Nozzles allow special rods that control the nuclear reaction to pass
through the lid. Until the Davis-Besse hole was discovered, the NRC did not consider
boric-acid leaks from cracked nozzles to be dangerous because it thought
the 605-degree heat from the reactor would turn the wet acid into harmless
dry power rather than eat through steel. The new program requires plants with the oldest lids to conduct the
tests every time they close for refueling - generally every two years - if
they have been operating at higher temperatures and generating electricity
for many years. Plants with less extreme operating records must conduct
instrument-aided inspections at least every other refueling shutdown. But plants with new lids have to do it only once during the next five
years - and subsequently once every fourth refueling shutdown or every
seven years. Sheron said he expects few plants will ultimately have to test every
two years because many are purchasing new reactor lids. Asked if lid replacement wasn't the agency's real objective, he said,
"I can't sit here and say that I've made the requirement so onerous that
this is the only way out. I'm just saying that's the reality of it - at
some point . . . industry has to do the cost-benefit [analysis] and say it
is cheaper to replace the vessel head and move into that low category and
not have to do these onerous inspections." To reach this Plain Dealer reporter: skoff@plaind.com, 216-999-4212
| ||||||||||||||||||||||||||||
About Us | Help/Feedback | Advertise With Us Use of this site constitutes acceptance of our User Agreement. Please read our Privacy Policy. ©2003 cleveland.com. All Rights Reserved.
| ||||||||||||||||||||||||||||