![]() |
| ||||||||||||
![]() |
\n');
}
if ( plugin ) {
document.write('');
} else if (!(navigator.appName && navigator.appName.indexOf("Netscape")>=0 && navigator.appVersion.indexOf("2.")>=0)){
document.write(' ');
}
//-->
| ||||||||||||
|
|
INSIDE The Plain Dealer » News » Business » Crime » Education » In-Depth » Lottery » NewsFlash » Opinion/Columns » PD Front Page » Politics » Traffic » Weather » News Obituaries » PD Obituaries » Paid Death Notices
|
| ||||||||||||||||||||||||||||||||||
News
Davis-Besse price tag may be $500 million 07/25/03
The cost of the extended shutdown of the Davis-Besse nuclear power
plant was nearly $450 million by the end of last month and will probably
exceed $500 million before the plant is ready to restart this fall. That's a far cry from plant owner FirstEnergy Corp.'s early time and
cost estimates. In a letter to investors a few days after major corrosion was found in
the reactor's lid in March 2002, the company had estimated repairs would
take up to 90 days and cost between $5 million and $10 million, plus
energy replacement costs. Two months later, FirstEnergy announced plans to replace the reactor
head at a cost of between $50 million and $75 million and have the plant
ready to restart by the last quarter of the year. The company also said it
planned another $50 million to $70 million in repairs to safety and other
systems. This week, the company said the power plant could be ready to restart
in September, 19 months after it shut down. Yesterday, that was changed to
"in the fall." A spokesman declined to be more specific. The Nuclear
Regulatory Commission has the final say on allowing the plant to resume
making electricity. The NRC also has many inspections to make on its restart checklist
after the company thinks the plant is ready. The Toledo-area plant was taken off line in February 2002 for refueling
and a special leak inspection requested by the NRC. The reactor did have
leaks, which had, over several years, corroded a hole nearly all the way
through the 6.63-inch-thick steel lid. Repairs to the reactor and several emergency systems - along with
normal maintenance that would have been done during routine refueling
shutdowns - had cost about $236 million at the end of June. Yesterday,the company estimated an additional $22 million will be spent
on plant repairs by year's end, taking the total bill to an estimated $258
million. The cost of buying replacement power came to $213 million by June 30
and is expected to run between $20 million and $25 million this month and
next before settling back down to $15 million per month during the fall.
In its most recent financial quarter, ended March 31, FirstEnergy
earned $138.8 million on revenues of slightly more than $3.2 billion. The
company plans to announce the second quarter earnings Aug. 5. Yesterday's revised estimates on cost and time were tied to a new
determination by Davis-Besse engineers that they will be able to
successfully modify the plant's high-pressure emergency pumps. A study had revealed that the twin 600-horsepower pumps, meant to
inject water into a reactor after it lost coolant, could be jammed by
debris in the water, which is also used to cool and lubricate the pumps'
bearings. Consulting engineers tried to add a "self-cleaning" debris screen and
to move an internal port directing water to the bearings, but the screens
themselves clogged in the testing of mock-ups. Testing began more that a month ago and reached a point yesterday at
which engineers are confident they have developed a working debris screen,
plant spokesman Richard Wilkins said. But testing will continue into next week on another modification,
perfected about 20 years ago by French nuclear authorities on whose design
the Davis-Besse pump is based, said Wilkins. That technique is to replace the bearings and other internal parts with
hardened parts that would grind up any debris that got into the pumps.
This French fix did not need a debris screen. "They are taking a suspenders-and-belt approach to the problem,"
Wilkins said, "to see what gives us the margin of safety we want." To reach this Plain Dealer reporter: jfunk@plaind.com, 216-999-4138
| ||||||||||||||||||||||||||||||||||||
About Us | Help/Feedback | Advertise With Us Use of this site constitutes acceptance of our User Agreement. Please read our Privacy Policy. ©2003 cleveland.com. All Rights Reserved.
| ||||||||||||||||||||||||||||||||||||