| June 27, 2008 Eric Solomon, Assistant Secretary for Tax Policy Dear Mr. Solomon, I am writing on behalf of Ohio
Citizen Action, a statewide
organization with 60,000 members.
Founded in 1975, Ohio Citizen Action has been
involved in
both
environmental and consumer issues involving Ohio Citizen Action has members in many of the communities who are members of American Municipal Power-Ohio (AMP-Ohio), and has been deeply involved for the past ten months in the debates over the proposed AMP-Ohio Generating Station (AMPGS). AMP-Ohio is proposing to build a 960 megawatt, pulverized coal plant, which would be financed by tax-exempt bonds. AMP-Ohio’s member communities have been asked to sign 50-year take-or-pay contracts to purchase “shares” of this facility. Background
on
AMP-Ohio coal plant AMP-Ohio began exploring plans
for
building a coal-fired
power plant in 2002, according to documents we have received through
public
records requests at the City of Since 2002, the schedule for plant development has repeatedly been delayed, and the cost estimates have continued to rise. In October 2005, AMP-Ohio cited the cost as $1.2 billion – by January 2008, the cost had more than doubled to $2.9 billion plus financing, with an “estimated” construction date beginning in 2009. In the fall of 2007, the plant became the subject of serious public debate because Ohio EPA issued the major air pollution permit, thus beginning a public comment process, and some city councils held public meetings to vote on whether to enter into the long-term contracts to purchase “shares” of the plant. Did
AMP-Ohio
member
communities have adequate information and time to consider the risks of
this
venture? Despite the major financial consequences of entering into a take-or-pay contract for a facility of this size, most communities conducted no independent investigation of the plans for the plant and relied on information provided by AMP-Ohio to determine whether this was a wise financial investment. To our knowledge, only Cleveland Public Power hired an outside firm, Burns and Roe, to review the plans for AMPGS, and Oberlin ultimately hired by an energy consulting firm to examine alternatives. AMP-Ohio’s contract required that their members had to vote by November 1, 2007 if they wanted to be able to consider opting out with no penalty by February 29, 2008. According to Ohio Citizen
Action’s
survey of all the
AMP-Ohio communities, all of the The
schedule
imposed
by AMP Ohio Citizen Action and several environmental policy organizations asked independent consultants to review the proposed plant, but the tight timeline meant that this information was not available until late January and early February 2008. Our organization mailed several studies (including the Scott Balice report, attached) to councilmembers around the state, but this was not an adequate substitute for thorough public meetings and discussion. Very few The issue was very controversial in Cleveland, which would be the biggest municipal owner of the plant, and Cleveland City Council decided to hire its own consultant very late in the process – so late, in fact that, Council had virtually no time to read or digest its own consultant’s report. The Council hired Ion Consulting, which made its one and only public presentation to the City Council Public Utilities Committee on February 22 – during the same meeting when the committee was forced to vote on the issue under AMP’s deadlines. The Ion report raised many red flags about the wisdom of Cleveland Public Power joining the project – even citing a scenario under which Cleveland Public Power could enter a “death spiral” (see p. 5 of the enclosed report). In the meantime, AMP-Ohio had
promised the communities that
its own engineering consultant, R.W. Beck, would produce a revised
feasibility
study in early 2008. R.W.
Beck had done
a study in June 2007, citing the cost of the plant as $2.5 billion plus
financing. The
revised study was
apparently submitted to AMP in late January 2008. AMP went to great
lengths to
keep information about the soaring costs of the project out of the
public eye. For
example, AMP contacted its member
utilities and invited some people to private meetings in early February
to
learn more about the new feasibility study.
AMP-Ohio planned to hold one of its regional
meetings in COMMITTEE MEMBERS PRESENT: Bruce OTHER COUNCIL MEMBERS PRESENT: Tom Palecek OFFICIALS PRESENT: Public Service Director Chris Easton, Asst. Dir. of Public Service Rob Peters, Utilities Manager Roger King [excerpt]
3.
AMPGS Meeting The
AMPGS meeting was an update on the AMP Ohio generating station project.
It was
not a public meeting. They were trying to avoid triggering the Sunshine
Law at
the meeting. It was a regional meeting for Utility Directors and
Service
Directors and it would be held in Because AMP-Ohio’s proceedings are not public, we do not know who was invited or included in these “regional”meetings, or what information participants were given. On Will the cost of the AMP-Ohio
plant continue to rise? Every consultant that
reviewed the R.W. Beck feasibility studies produced by AMP-Ohio flagged
a key
issue: the question of whether AMP-Ohio will be able to secure a fixed
price
from its major contractors. All of the independent studies which were done cited various factors which could cause the plant to continue to escalate in cost. I have attached hard copies of these reports, and they can also be found at the following electronic links:
1) Burns and Roe report done for Cleveland Public Power: http://www.ohiocitizen.org/campaigns/coal/BREI%20Consulting%20Engineer%20Report%20FINAL%20101607.pdf 2) Scott Balice report done for
Environmental Law and 3) Synapse Energy Economics report done for NRDC: http://docs.nrdc.org/globalwarming/glo_08021401A.pdf 4) Ion Consulting report done for Cleveland City Council: http://www.clevelandcitycouncil.org/Home/Committees/PublicUtilities/AMPGS/tabid/443/Default.aspx (click on Ion Consulting report on the bottom) 5) T.R. Rose Associates analysis of the contract: http://www.ohiocitizen.org/campaigns/coal/ampohio2.doc According to emails from
AMP-Ohio to its members, obtained through a recent public records
request,
AMP-Ohio was considering bids from three major contractors:
Bechtel,
SNC-Lavalin, and Shaw, Stone, and Webster. Emails
obtained through
a public records request state that the AMP-Ohio board made a
decision on
selecting a contractor at its March 20, 2008 board meeting, although
the name
of the selected contractor has not yet been released to the public, and
there
has been no public information about whether they were able to provide
any
price guarantees. According to AMP-Ohio’s original timeline, final
negotiations
with a contractor would take place over the next several months. Has AMP-Ohio provided accurate information about
whether it has
sufficient commitments to move forward with this project? The Power Sales Contract for
this
plant stated it would only
go into effect once AMP-Ohio reached the level of 750 megawatts worth
of shares. Also,
once that level of shares was reached,
AMP-Ohio would form a participants committee.
At the Cleveland City Council hearing on But if AMP-Ohio had 750 megawatts worth of commitments by February 22, 2008, why has it still not moved forward with the participants committee four months later? Despite all the pressure which AMP Ohio put on its member communities to make a final decision by February 29, 2008, AMP-Ohio still has not signed the contract with the City of Cleveland nor formed the required participants committee as of June 24, 2008 (per email communication with Cleveland Public Power, 6/24/08). Ohio Citizen Action surmises, based on our survey of the municipalities, that AMP-Ohio has not reached the 750 megawatt commitment level. In the contract AMP-Ohio sent to its members to sign, a schedule entitled “(Preliminary) Schedule of Participants “ listed a total of 958 megawatts in projected shares from its members (see http://www.ohiocitizen.org/campaigns/coal/amp_ohio.pdf). However, AMP-Ohio did not secure this
amount of commitments from its members. Ohio Citizen Action
has
independently contacted all of AMP-Ohio’s member communities and has
documented
that decreases
in commitments total at least 260 megawatts from the original plan, and
increases in commitments add up to less than 10 megawatts. Thus, at
best, AMP-Ohio fell short of
its original schedule of commitments by approximately 250 megawatts –
causing
it to fall short of its 750 megawatt minimum goal from its original
list of
members.
It may be
counting on heavily marketing the plant
to some of its newer members in Will
the AMP-Ohio plant be subject to the “carbon principles”? As part of its campaign to get communities to sign on to the AMP-Ohio plant, AMP-Ohio circulated a February 7, 2008 letter from J.P. Morgan Chase saying it would not apply the so-called “carbon principles” to the AMP-Ohio plant. These principles were spawned by the many uncertainties surrounding the costs of carbon regulation. AMP-Ohio also posted this letter on their website (it has since been removed). However, on March 20, 2008, the Wall Street Journal reported that JP Morgan Chase and the other financial institutions had decided to examine how to apply the carbon principles to municipally-owned coal plants. Indeed, the carbon principles, which are posted on www.carbonprinciples.org, state that they plan to cover public power projects within six months of their issuance. Because the AMP-Ohio project
would be
funded by municipal
electric ratepayers, and the cities are signing “take or pay
contracts,” bond
buyers are likely to assume that there is little financial risk. Residents and municipal
governments will
simply have to pay whatever the cost of their electric bill is every
month. However, the
financial condition
of many of Comptroller Thompson’s letter raises questions about the increasingly speculative nature of these investments. If it were clear to me that the local officials who are making these decisions were fully informed on these issues I would have to be content that they were made in good faith. However, the issue of rising construction costs and rising coal prices have been swept aside by the project developer as if they are under control. They have never been able to give communities a solid number on how much this electricity would cost them. Transparency is non-existent. The regulatory vagaries that caused the Rural Utility Services to suspend coal plant lending are being ignored.. We urge you to investigate this situation, and would be happy to provide you with further information. Sincerely, Sandy Buchanan, Executive Director Ohio Citizen Action Attachments: Graph of rising cost of plant Burns and Roe report Scott-Balice Study Synapse Study T.R. Rose Associates Report Ion Consulting Report |
|
|